Manager's Report — 02 Oct 2026: Pulte Planned Unit Development Heads to Public Hearing
A quiet week at the Village Board level, but a busy one on the ground: road milling, sewer lining, and hydrant painting all advance, while a major residential development proposal heads to a public hearing next week.
Full agenda — click any item to expand
Upcoming Meetings
There are no Village Board meetings scheduled for the week ahead. However, a Plan Commission Special Meeting is set for Tuesday, October 6, 2026, at 6 p.m. at Techny Prairie Activity Center. That meeting will include a public hearing on PCD-26-05, an application by Pulte Home Company, LLC for a Planned Unit Development at 1901–1975 Cherry Lane. The meeting will be livestreamed on the Village of Northbrook Facebook page and the Village Meeting Archive Portal.
Activity Reports
The weekly Police Bulletin has been updated for the week ending October 2, 2026.
The Zoning Board of Appeals approved three applications at its regular meeting on Monday, September 28, 2026:
- A front yard setback variation for an addition at 3722 Pebble Beach Road
- A rear yard setback variation for an addition at 1335 Western Avenue
- A rear yard setback variation for an addition at 4165 Cardinal Court
A new business license was issued to Dr. Pearl Park DO, a medical clinic for virtual health encounters at 666 Dundee Rd #305.
The Village welcomed Layla Werner as the new Deputy Director of Public Works, starting September 28, 2026. The Village also congratulated Northbrook Police Sergeant Baiocchi, Commander Tadley, and Deputy Chief of Technical Services Ferguson on their promotions; their swearing-in ceremony was held September 29, 2026.
Year-to-date development information — including commercial building permits, new business licenses, applications under review, and active construction projects — is available on the Village website.
Save the Date
Fire Department Open House — Saturday, October 3 The Northbrook Fire Department will hold its annual Open House at Fire Station 10, 650 Huehl Road, from 9 a.m. to noon. Families and children can explore fire trucks and equipment, meet firefighters, watch special team demonstrations, and learn fire safety tips. The event is held in recognition of Fire Prevention Week. Parking is available at 655 Huehl Road.
Plan Commission Special Meeting — Tuesday, October 6 The Plan Commission will hold a special meeting at 6 p.m. at Techny Prairie Activity Center to conduct a public hearing on the Pulte Home Company Planned Unit Development application at 1901–1975 Cherry Lane (PCD-26-05).
125th Anniversary Open House — Sunday, November 15 The Village will celebrate its 125th anniversary with a community Open House at Village Hall from 2–4 p.m. Activities include music, a Village birthday cake, Touch-a-Truck, historical displays, and local artwork. At 3:15 p.m., attendees are invited to help recreate a community photograph originally taken in 1925. More information is available at northbrook125.com.
Read more
Project Updates
Skokie Boulevard Resurfacing During the week of September 28, the contractor closed curbside lanes and replaced sections of curb and gutter along both sides of Skokie Boulevard between the I-94 Edens Expressway bridge and the southern end of the project corridor. Crews adjusted catch basins and inlets and completed remaining curb replacements, then began milling the existing roadway surface in the outside lane closure areas. During the week of October 5, curbside lanes will be closed from 7 a.m. to 4 p.m. for continued milling; closures will then shift to inside lanes until milling throughout the project limits is complete. Questions can be directed to Engineering Technician Jim Huff at 847-272-4711 or James.Huff@northbrook.il.us.
Fire Hydrant Painting Beginning October 2 (weather permitting), contractors started the Village's Fire Hydrant Painting Program. This year's work covers 327 Village-owned hydrants in the central portion of town, beginning in the northwest and moving southeast. Work is expected to be completed by October 16.
Sewer Lining Installation Beginning the week of October 5, the Village's contractor will begin sewer lining work. The process involves inserting a durable liner into existing sanitary sewer pipes to address cracks and deterioration. The work requires no excavation, typically takes a few hours per location, and extends the useful life of sewer infrastructure. Questions can be directed to the Public Works Department at 847-272-4711.
Crestwood Senior Housing Roof Replacement During the week of September 28, the contractor substantially completed installation of the cap sheet on the southern building. Weather permitting, crews expect to complete remaining flashing details, surface coating, and metal detail work on the southern building during the week of October 5.
FY 26-27 Concrete Street Patching Improvements
- Charlemagne Subdivision: The contractor continued landscape and mailbox restoration during the week of September 28 and anticipates beginning joint sealing for replaced concrete panels the week of October 5.
- Sky Harbor Business Park: During the week of September 28, the contractor completed saw cutting of panels requiring replacement on Wainwright Drive, Melvin Drive, and MacArthur Boulevard. During the week of October 5, the contractor expects to pour new concrete panels on Wainwright Drive and Melvin Drive and begin joint sealing. Residents and businesses should expect intermittent lane and parking restrictions near active work areas.
Questions about the street patching project can be directed to Project Resident Engineer Luis Uriostegui at 847-664-4118 or Luis.Uriostegui@northbrook.il.us.